(f)     Change in Plans.  When major revisions are decided on after the original construction permit(s) have been issued, an additional fee of fifty percent (50%) of the original construction permit fee(s) shall be collected for consideration of such revisions.  (Ord. 2012-78.  Passed 11-19-12.)

 
1311.03  ELECTRICAL PERMIT AND INSPECTION FEES.

     Beginning work without permits, penalty is double the cost of all permits required.

     (a)     New Construction.

          (1)     Residential: One, Two and Three family Dwellings.

               A.     Base fee per structure or unit

$150.00

               B.     Plus a fee for each lighting outlet or fixture 

2.00

               C.     All accessory structures and appurtenances

                    thereto (including garages, greenhouses,

                    sheds, etc.)

 

                    1.     Base fee per structure or unit

50.00

                    2.     Plus a fee for each lighting outlet

                         or fixture

2.00


               D.     A fee for each of the following items included,

                    in any electrical installation, as follows:

                    1.     Ranges and similar heating devices

6.00

                    2.     When fixtures contain more than four

                         florescent tubes, each four tubes shall

                         be deemed to be a separate lighting

                         fixture, at

2.00

                    3.     Motors up to 3/4 HP

3.00


                    4.     For each power outlet, including

                         transformers, capacitors, generators,

                         batteries, rectifiers, motors including

                         controls, distributions and connections

                         as follows:

                         a.     From 3/4 HP to, but not to

                              exceed 3 HP

5.00

                         b.     Over 3 HP but not to exceed

                              5 HP  

10.00

                         c.     Over 5 HP but not to exceed

                              10 HP

15.00

                         d.     Over 10 HP but not to exceed

                              15 HP     

20.00

                         e.     In excess of 15 HP

28.00


                    5.     For each power outlet requiring a

                         220 volt circuit for operation of an

                         electrical device as follows:

 

                         a.     Not to exceed 3 KW

6.00

                         b.     Over 3 KW but not to exceed

                              10 KW

9.00

                         c.     Over 10 KW

15.00

                    6.     Junction boxes (used or unused)

2.00

                    7.     Per six-foot section of multi-outlet

3.00

                    8.     Thermostats

2,00

                    9.     Telephone, cable TV or antenna outlets

2.00

                    10.     Bells and alarms (smoke, fire or security)

2.00

                    11.     Transformers

100.00

                    12.     High intensity fixtures

2.00

                    13.     Switches

2.00

                    14.     Battery packs (emergency lighting)

2.00

                    15.     Exit signs (AC or DC)

2.00

                    16.     Panels (each)

50.00

                    17.     Metering (each)

25.00

                    18.     Ground fault circuit interceptors

5.00

                    19.     Grounding methods (each)

5.00

                    20.     Lighting track and accessories (each

                         six feet)

3.00

                    21.     Temporary lighting (per floor or site)

20.00

                    22.     Gasoline dispensing pumps (each)

10.00

                    23.     Bath fans

10.00

                    24.     Fixed outdoor lighting (per pole)

10.00

                    25.     Wind Turbine

1,000.00

                    26.     Conduit

10 per 100 feet

                    27.     Lightning Arrestors

10.00

                    28.     Fuse Cutout

10.00

                    29.     Solar Panel

50.00

                    30.     Any electrical outlets or equipment

                         not listed above     

10 per $100 of total project cost


               E.     Heating outlets:

                    1.     Up to 10 KW

8.00

                    2.     Over 10 KW to 15 KW

10.00

                    3.     Over 15 KW to 20 KW

15.00

                    4.     Over 20 KW to 25 KW

20.00

                    5.     Over 25 KW

25.00


          (2)     All other buildings.

               A.     Base fee per structure or unit

250.00

               B.     Plus a fee for each lighting outlet or fixture

2.00

               C.     A fee for each of the following items included,

                    in any electrical installation, as follows:

 

                    1.     Ranges and similar heating devices

6.00

                    2.     When fixtures contain more than four

                         florescent tubes, each four tubes shall

                         be deemed to be a separate lighting

                         fixture, at

2.00

                    3.     Motors up to 3/4 HP

3.00

                    4.     For each power outlet, including

                         transformers, capacitors, generators,

                         batteries, rectifiers, motors including

                         controls, distributions and connections

                         as follows:

 

                         a.     From 3/4 HP to, but not to

                              exceed 3 HP

5.00

                         b.     Over 3 HP but not to exceed

                              5 HP      

10.00

                         c.     Over 5 HP but not to exceed

                              10 HP

15.00

                         d.     Over 10 HP but not to exceed

                              15 HP

20.00

                         e.     In excess of 15 HP

28.00

                    5.     For each power outlet requiring a

                         220 volt circuit for operation of an

                         electrical device as follows:

 

                         a.     Not to exceed 3 KW

6.00

                         b.     Over 3 KW but not to exceed

                              10 KW     

9.00

                         c.     Over 10 KW

15.00

                    6.     Junction boxes (used or unused)

2.00

                    7.     Per six-foot section of multi-outlet

3.00

                    8.     Thermostats

2.00

                    9.     Telephone, cable TV or antenna outlets

2.00

                    10.     Bells and alarms (smoke, fire or security)

2.00

                    11.     Transformers      (per 10 w of voltage)     

10.00

                    12.     High intensity fixtures

2.00

                    13.     Switches

2.00

                    14.     Battery packs (emergency lighting)

2.00

                    15.     Exit signs (AC or DC)

2.00

                    16.     Panels (each)

50.00

                    17.     Metering (each)     

25.00

                    18.     Ground fault circuit interceptors

5.00

                    19.     Grounding methods (each)

5.00

                    20.     Lighting track and accessories (each

                         six feet)

3.00

                    21.     Temporary lighting (per floor or site)

20.00

                    22.     Gasoline dispensing pumps (each)

25.00

                    23.     Bath fans

10.00

                    24.     Fixed outdoor lighting (per pole) 

10.00

                    25.     Wind Turbine

1,000.00

                    26.     Conduit

10 per 100 feet

                    27.     Lightning Arrestors

10.00

                    28.     Fuse Cutout

10.00

                    29.     Solar Panel

50.00

                    30.     Any electrical outlets or equipment

                         not listed above

                         project cost

10 per $100 of total


               D.     Heating outlets:

                    1.     Up to 10 KW

5.00

                    2.     Over 10 KW to 15 KW

10.00

                    3.     Over 15 KW to 20 KW

15.00

                    4.     Over 20 KW to 25 KW

20.00

                    5.     Over 25 KW

25.00


     (b)     Additions, Alterations, Renovations or Repairs.

          (1)     Residential: One, two and three family dwellings.

 

               A.     Base fee per structure or unit

50.00

               B.     Plus any applicable fees as per

                    new construction

 

               C.     Plus a fee for each lighting outlet or fixture

2.00

               D.     All accessory structures and appurtenances

                    thereto (including garages, greenhouses,

                    Sheds, etc.)

 

                    1.     Base fee per structure or unit

25.00

                    2.     Plus a fee for each lighting outlet

                         or fixture

2.00

               E.     A fee for each of the following items included,

                    in any electrical installation, as follows:

 

                    1.     Ranges and similar heating devices

6.00

                    2.     When fixtures contain more than four

                         florescent tubes, each four tubes shall

                         be deemed to be a separate lighting

                         fixture, at

2.00

                    3.     Motors up to 3/4 HP

3.00

                    4.     For each power outlet, including

                         transformers, capacitors, generators,

                         batteries, rectifiers, motors including

                         controls, distributions and connections

                         as follows:

 

                         a.     From 3/4 HP to, but not to

                              exceed 3 HP

5.00

                         b.     Over 3 HP but not to exceed

                              5 HP 

10.00

                         c.     Over 5 HP but not to exceed

                              10 HP

15.00

                         d.     Over 10 HP but not to exceed

                              15 HP

20.00

                         e.     In excess of 15 HP

28.00

                    5.     For each power outlet requiring a

                         220 volt circuit for operation of an

                         electrical device as follows:

 

                         a.     Not to exceed 3 KW

6.00

                         b.     Over 3 KW but not to exceed

                              10 KW

9.00

                         c.     Over 10 KW

 

                    6.     Junction boxes (used or unused)

2.00

                    7.     Per six-foot section of multi-outlet

3.00

                    8.     Thermostats

2.00

                    9.     Telephone, cable TV or antenna outlets

2.00

                    10.     Bells and alarms (smoke, fire or security)

2.00

                    11.     Transformers      (per 10 w of voltage)

10.00

                    12.     High intensity fixtures

2.00

                    13.     Switches

2.00

                    14.     Battery packs (emergency lighting)

5.00

                    15.     Exit signs (AC or DC)

2.00

                    16.     Panels (each)

50.00

                    17.     Metering (each)

25.00

                    18.     Ground fault circuit interceptors

5.00

                    19.     Grounding methods (each)

5.00

                    20.     Lighting track and accessories (each

                         six feet)

3.00

                    21.     Temporary lighting (per floor or site)

20.00

                    22.     Gasoline dispensing pumps (each)

25.00

                    23.     Bath fans

10.00

                    24.     Fixed outdoor lighting (per pole)  

10.00

                    25.     Wind Turbine

1,000.00

                    26.     Conduit

10 per 100 feet

                    27.     Lightning Arrestors

10.00

                    28.     Fuse Cutout

10.00

                    29.     Solar Panel

50.00

                    30.     Any electrical outlets or equipment

                         not listed above

10 per $100 of total project cost


          (2)     All other buildings.

 

               A.     Base fee per structure or unit

200.00

               B.     Plus any applicable fees as per new

                    construction

 

     (c)     Illuminated Signs. Permanent signs base fee

100.00

          (1)     Plus per 10 sq. ft. of signage

5.00

     (d)     Miscellaneous Electric Permit Fees.

 

          (1)     Inspection of carnival, bazaar and other similar

               temporary electrical installations or facilities

250.00

          (2)     Temporary service for construction

150.00

          (3)     Fixed outdoor lighting (per pole)

10.00


     (e)     Change In Electric Plans.  When major revisions are decided on after the original construction permit(s) have been issued, an additional fee of fifty percent (50%) of the original construction permit fee(s) shall be collected for consideration of such revisions.  (Ord. 2012-78.  Passed 11-19-12.)

 
1311.04  PLUMBING PERMIT AND INSPECTION FEES.

     Beginning work without permits, penalty is double the cost of all permits required.

     (a)     New Construction.

          (1)     Residential: One, two and three family dwellings.

               A.     Base fee per structure or unit

$100.00

               B.     Connection to sanitary sewer  

1,000.00

               C.     Connection to storm sewer

1,000.00

               D.     Installation of any of the following

                    as indicated:

 

                    1.     Water closet     

3.00

                    2.     Bathtub

3.00

                    3.     Shower stall

3.00

                    4.     Lavatory

3.00

                    5.     Washing machine     

6.00

                    6.     Kitchen sink

3.00

                    7.     Laundry tray

3.00

                    8.     Domestic hot water heater

6.00

                    9.     Floor drain

3.00

                    10.     Catch basins

25.00

                    11.     Water filter or conditioning equipment

6.00

                    12.     Dishwasher

3.00

                    13.     Sump pump

6.00

                    14.     Garbage disposal unit

3.00

                    15.     Bar sink

3.00

                    16.     Jacuzzi or hot tub

35.00

                    17.     Access panel

6.00

                    18.     Water distribution system

100.00

                    19.     Air admittance valve

10.00

                    20.     Back water valve     

35.00

                    21.     Underground piping sanitary/

                         storm water

10 per 100 feet

                    22.     Any installation of any other item legally

                         considered of residential nature

10.00

                    23.     Water tap-in fee

1,500.00

                    24.     Gas line

100.00

                    25.     Water meters

(see current Water Dept. price list)


          (2)     All other buildings.

               A.     Base fee per structure or unit

250.00

               B.     Connection to sanitary sewer

2,000.00

               C.     Connection to storm sewer

2,000.00

               D.     Installation of any of the following equipment:

 

                    1.     Any applicable fees for installation of

                         any item as set out in Section

                         1311.04(a)(1)D. shall be computed at

                         double the schedule fees.

 

                    2.     Installation of any of the following:

 

                         a.     Interceptors

25.00

                              plus .10 per gallon

 

                         b.     Janitor's sink

6.00

                         c.     Shampoo bowl

6.00

                         d.     Urinal

6.00

                         e.     Drinking fountain

6.00

                         f.     Dental chair

6.00

                         g.     Pot Sink     

12.00

                         h.     Hot water heater up to

                              150 gallons

50.00

                         i.     Hot water heater  from 150

                              gallons to 300 gallons

100.00

                         j.     Hot water heater over

                              300 gallons

200.00

                         k.     Backflow prevention devices:

40.00

                              k-1: Two inch and under

50.00

                              k-2: 2½ and larger

100.00

                         l.     Trap priming devices

5.00

                         m.     Indirect wastes

5.00

                         n.     Gas line

200.00

                         o.     Back water valves

50.00

                         p.     Underground piping sanitary/

                              storm water

20 per 100 feet

                         q.     Water tap-in fee

2,500.00

                         r.     Water meters (see current Water Dept. price list)

 

 

     (b)     Additions, Alterations, Renovations or Repairs.

          (1)     Residential: One, two and three family dwellings.

               A.     Base fee per structure or unit

50.00

               B.     Connection to sanitary sewer

1,000.00

               C     Connection to storm sewer

1,000.00

               D.     Installation of any of the following

                    as indicated

 

                    1.     Water closet

5.00

                    2.     Bathtub

5.00

                    3.     Shower stall

5.00

                    4.     Lavatory

5.00

                    5.     Washing machine

6.00

                    6.     Kitchen sink

3.00

                    7.     Laundry tray

3.00

                    8.     Domestic water heater

10.00

                    9.     Floor drain

3.00

                    10.     Catch basins

25.00

                    11.     Water filter or conditioning equipment

6.00

                    12.     Dishwasher

3.00

                    13.     Sump pump

6.00

                    14.     Garbage disposal unit

3.00

                    15.     Bar sink

3.00

                    16.     Jacuzzi or hot tub     

50.00

                    17.     Access panel

6.00

                    18.     Water distribution system

100.00

                    19.     Air admittance valve

10.00

                    20.     Water control/Waterproofing

150.00

                    21.     Gas line

100.00

                    22.     Back water valves

35.00

                    23.     Underground piping sanitary/

                         storm water

10 per 100 feet

                    24.     Any installation of any other item

                         legally considered of residential nature

10.00

                    25.     Water tap-in fee

1,500.00

                    26.     Water meters (see current Water Dept. price list)

 

               E.     Alterations to water distribution system

25.00

               F.     Repair or replace water service or sewers

100.00

          (2)     All other buildings.

 

               A.     Base fee per structure or unit

200.00

               B.     Connection to sanitary sewer

1,000.00

               C.     Connection to storm sewer 

1,000.00

               D.     Plus any applicable fees as set out

                    in Section 1311.04(a)(2)D. hereof,

                    under new construction at the same fee.

 

               E.     Alterations of water distribution system

100.00

               F.     Repair or replace water service or sewers  

100.00

     (c)     Underground Storage Tanks.  Any underground storage

          tank shall require a fee as follows:

 

          (1)     Base fee per tank

250.00

          (2)     Plus a fee for each 1000-gallon capacity, or fraction

               thereof

5.00

     (d)     Above Ground Storage Tanks.  Any above ground storage

          tank shall require a fee as follows:

 

          (1)     Base fee per tank     

200.00

          (2)     Plus a fee for each 100 gallon capacity, or

               fraction thereof 

5.00


     (e)     Change In Plumbing Plans. When major revisions are decided on after the original construction permit(s) have been issued, an additional fee of fifty percent (50%) of the original construction permit fee(s) shall be collected for consideration of such revisions.

          (Ord. 2012-78.  Passed 11-19-12.)

 
1311.05  HEATING, VENTILATING, AIR CONDITIONING AND REFRIGERATION FEES.

     Beginning work without permits, penalty is double the cost of all permits required.

     (a)     New Construction.

          (1)     Residential: One, two and three-family dwellings.

               A.     Base fee

100.00

               B.     Plus a fee for the installation of each new

                    warm air furnance and boiler (including

                    solar energy) as follows:

 

                    1.     Up to and including 150,000 BTUH

                         input

20.00

                    2.     Over 150,000 BTUH input capacity

25.00

                         Plus a fee for each additional

 

                    3.     100,000 BTUH, or fraction thereof

6.00

               C.     New air conditioning base fee (no ductwork)

50.00

                    1.     Up to and including 1 ton capacity

5.00

                    2.     Up to and including 2 ton capacity

10.00

                    3.     Up to and including 3 ton capacity

15.00

                    4.     3 ton capacity and over

30.00

               D.     New air conditioning base fee (with ductwork)

100.00

               E.     All accessory structures and

                    appurtenances thereto as follows:

 

                    1.     Base fee per structure or unit

10.00

                    2.     Plus any applicable fees for

                         equipment stipulated elsewhere

                         in this section.

 

          (2)     All other buildings.

 

               A.     Base fee per structure or unit for the installation

                    of each new warm air furnance and boiler

                    (including solar energy) as follows:

200.00

               B     Plus a fee for each of the following:

 

                    1.     Up to and including 150,000 BTUH

                         input

30.00

                    2.     Over 150,000 BTUH input

40.00

                    3.     Plus a fee for each 100,000 BTUH

                         at the rate of

10.00

               C.     Installation of each air conditioning

                    unit: (Base Fee)

150.00

                    1.     Up to and including 3 ton capacity

30.00

                    2.     Up to and including 6 ton capacity

40.00

                    3.     Up to and including 10 ton capacity

50.00

                    4.     10 ton capacity and over

70.00

               D     New air conditioning base fee (with ductwork)

150.00

               E     All accessory structures and appurtenances

                    thereto as follows:

 

                    1.     Base fee per structure or unit

30.00

                    2.     Plus any applicable fees for

                         equipment stipulated elsewhere

                         in this section.

 

     (b)     Additions, Alterations or Repairs.

          (1)     Residential: One, two and three family dwellings.

 

               A.     Base fee per structure or unit

75.00

               B.     Plus a fee for the installation of each new

                    warm air furnace and boiler (including solar

                    energy) as follows: 

 

                    1.     Up to and including 150,000 BTUH

                         input

20.00

                    2.     Over 150,000 BTUH input capacity

25.00

                    3.     Plus a fee for each additional

                         100,000 BTUH, or fraction thereof

6.00

               C.     New air conditioning base fee (no duct work)

75.00

                    1.     Up to and including 1 ton capacity

5.00

                    2.     Up to and including 2 ton capacity

10.00

                    3.     Up to and including 3 ton capacity

15.00

                    4.     3 ton capacity and over

30.00

               D.     New air conditioning base fee (with ductwork)

100.00

               E.     All accessory structures and

                    appurtenances thereto as follows:

 

                    1.     Base fee per structure or unit

10.00

                    2.     Plus any applicable fees for

                         equipment stipulated elsewhere

                         in this section.

 

          (2)     All other buildings.

 

               A.     Base fee per structure or unit for the installation

                    of each new warm air furnance and boiler

                    (including solar energy) as follows:

200.00

               B.     Plus a fee for each of the following:

 

                    1.     Up to and including 150,000 BTUH

                         input

30.00

                    2.     Over 150,000 BTUH input

40.00

                    3.     Plus a fee for each 100,000 BTUH

                         at the rate of

10.00

               C.     Installation of each new air conditioning

                    unit:     (Base Fee)

150.00

                    1.     Up to and including 3 ton capacity

30.00

                    2.     Up to and including 6 ton capacity

40.00

                    3.     Up to and including 10 ton capacity

50.00

                    4.     10 ton capacity and over

70.00

               D.     Installation of each new air conditioning

                    unit: (Base Fee)

150.00

               E.     All accessory structures and appurtenances

                    thereto as follows:

 

                    1.     Base fee per structure or unit

30.00

                    2.     Plus any applicable fees for

                         equipment stipulated elsewhere

                         in this section.

 

          (3)     All buildings and/or installation where applicable.

               A.     Overhead, wall mounted and/or space heating

                    appliances, whether electric, gas or oil

                    fueled as follows: (Base Fee)

200.00

                    1.     Up to and including 75,000

                         BTUH input

25.00 pu

                    2.     Over 75,000 BTUH input capacity

50.00 pu

                    3.     Plus a fee for each additional 10,000

                         BTUH input or fraction thereof at

                         the rate of

4.00

               B.     Installation of gas or electric infrared

                    units as follows:    (Base Fee)

200.00

                    1.     Up to and including 50,000

                         BTUH input

12.00

                    2.     Over 50,000 BTUH input capacity

15.00

                    3.     Plus a fee for each additional

                         10,000 BTUH input or fraction

                         thereof     

4.00

               C.     Installation of related equipment:  Base fee of

150.00

                    1.     Back flow device - Boiler only

50.00

                    2.     Solid fuel appliances and stoves  

100.00

                    3.     Commercial cook line hood

100.00

                    4.     Hood fire suppression system  

100.00

                    5.     Air cleaner

50.00

                    6.     Fire dampers

50.00

                    7.     Chimneys

100.00

                    8.     Masonry chimneys 

100.00

                    9.     Roof top units (sight buffering)

20.00

                    10.     Roof top units (cat walk)

20.00

                    11.     Roof top units (service outlets)

10.00

                    12.     Flue dampers

5.00

                    13.     Humidifier assembly

20.00

               D.     Refrigeration (pounds of refrigerant in system)

 

                    1.     One pound to five

10.00

                    2.     Five pound(s) to twenty

20.00

                    3.     Twenty pound(s) to one hundred

40.00

                    4.     One hundred pounds and over

60.00


     (c)     Change In Plans.  When major revisions are decided on after the original construction permit(s) have been issued, an additional fee of fifty percent (50%) of the original construction permit fee(s) shall be collected for consideration of such revisions.  (Ord. 2012-78.  Passed 11-19-12.)

 
1311.06  FIRE PROTECTION SYSTEM PERMIT AND INSPECTION FEES.

     Beginning work without permits, penalty is double the cost of all permits required.

     (a)     New Construction and Additions, Alterations and Repairs.

          (1)     Residential: One, two and three family dwellings.

               A.     Base fee per structure or unit

$100.00

               B.     Plus a fee per head or nozzle

2.00

               C.     Fire and Alarm Panels

25.00

               D.     Installation of any of the following:  Base fee

100.00

                    1.     Fire Department connections

25.00

                    2.     Yard hydrants

25.00

                    3.     Stand pipes 

25.00

                    4.     Fire extinguishers

10.00

                    5.     Back flow prevention device

25.00

                    6.     New fire service water line 

                         (per inspection)     

50.00

                    7.     Hoods

25.00

                    8.     Supp. Open & Base

2.00

                    9.     Chimney - Mason

10.00

                    10.     Chimney - Metal     

10.00

                    11.     Alarms Opening

2.00

                    12.     Solid Fuel Appliance

10.00

                    13.     Access Panel

2.00

          (2)     All other buildings.

 

               A.     Base fee per structure or unit

200.00

               B.     Plus a fee per head or nozzle

3.00

               C.     Fire and Alarm Panels

25.00

               D.     Installation of any of the following:  Base fee

200.00

                    1.     Fire Department connections

50.00

                    2.     Yard hydrants

50.00

                    3.     Stand pipes 

50.00

                    4.     Fire extinguishers

10.00

                    5.     Back flow prevention device

50.00

                    6.     New fire service water line 

                         (per inspection)

100.00

                    7.     Hoods

50.00

                    8.     Supp. Open & Base

2.00

                    9.     Chimney - Mason

25.00

                    10.     Chimney - Metal     

25.00

                    11.     Alarms Opening     

5.00

                    12.     Solid Fuel Appliance

25.00

                    13.     Access Panel

5.00


     (b)     Change In Plans. When major revisions are decided on after the original construction permit(s) have been issued, an additional fee of fifty percent (50%) of the original construction permit fee(s) shall be collected for consideration of such revisions.

          (Ord. 2012-78.  Passed 11-19-12.)

 
1311.07   ZONING PERMIT AND INSPECTION FEES.

     (a)     Zoning Permit (Site plan, Landscaping plan, Lighting plan individually or in combination).

 

          (1)     Residential: One, two and three-family dwellings.

$100.00

          (2)     All other buildings.

250.00

  

     (b)     Planning Commission Review Fees.

 

          (1)     Residential: One, two and three-family dwellings.

 

               A.     Subdivision

35.00/lot

               B.     Variance

50.00

               C.     Conditional use

100.00

               D.     Planned Unit Development

100.00

               E.     Other residential applications

35.00

          (2)     All other buildings.

 

               A.     Variance

75.00

               B.     Conditional use

150.00

               C.     Planned Unit Development

150.00

               D.     Business sign

50.00

               E.     Other applications, by building area

 

                    1.     4,000 SF and less     

250.00

                    2.     4,001 SF - 10,000 SF

300.00

                    3.     10,001 SF - 20,000 SF

350.00

                    4.     20,001 SF - 50,000 SF

500.00

                    5.     50,001 SF and greater

750.00

          (3)     Miscellaneous.

 

               A.     Zoning map amendment

50.00

               B.     Public hearing bond

50.00

                    The City of Berea reserves the right to request

                    additional bond money, should the cost of mailings

                    exceed $50.00

 
  

     (c)     Heritage Architectural Review Board ("HARB") fees.

 

          (1)     HARB review

 

     (d)     Sustainability zoning permit and review fees.

          (1)     Residential: One, two and three-family dwellings.

 

               A.     Rain barrels

Free

               B.     Wind conversion

50.00

                    plus a fee of $10.00 per $1,000.00 of

                    total project cost

 

               C.     Solar energy system

50.00

                    an electrical permit is also required,

                    see Section 1311.03

 

               D.     Green roof system

50.00

               E.     Geothermal wells

50.00

                    plus a fee of $100.00 per well

 

          (2)     All other buildings.

 

               A.     Rain barrels

Free

               B.     Wind conversion

100.00

                    plus a fee of $10.00 per $1,000.00 of

                    total project cost

 

               C.     Solar energy system

100.00

                    an electrical permit is also required,

                    see Section 1311.03

 

               D.     Green roof system

100.00

                    plus a fee of $10.00 per 100 SF of roof area

 

               E.     Geothermal wells

250.00

     plus a fee of $100.00 per well

 
  

     (e)     Miscellaneous.

 

          (1)     Residential dumpsters and PODs     

10.00

               plus a fee of $1 per day for each day over 10 days

 

          (2)     Farmer's Market

100.00

          (3)     Special recreational vehicle parking permit

10.00

               plus a fee of $1.00 per day for each day over 10 days

 

(Ord. 2012-78.  Passed 11-19-12.)

 
1311.08  ANNUAL INSPECTION AND REVIEW FEE FOR TAX-ABATED COMMERCIAL AND INDUSTRIAL PROPERTIES.

     There is hereby imposed upon the owners of tax-abated commercial and/or industrial real properties located in the City an annual review and inspection fee of $800 per tax-abated parcel, and payment of same shall be made to the City annually on or before completion of the annual review and inspection by the City of Berea.

(Ord. 2012-78.  Passed 11-19-12.)